With the help of Cleary Contracting Ltd, The Glassblowing Workshop in Chemistry and Chemical Engineering can now provide highly skilled specialist design, manufacturing and repair service to teaching and research within the School, University and outside agencies.
Client Name: Queens University Belfast
Project Details:
The project was completed within the David Kier Building. The building remained occupied throughout the course of the works and the works were phased to allow the staff to relocate whilst the works took place. The project was heavily influenced with mechanical and electrical services and planned shutdowns/changeover’s were key to the success of the project. The finishes within the main teaching lab included Altro Resin floor finishes and Threspa fitted furniture work stations for students.
Duration of contract: 6 months
Location: University Road, Belfast
Architect: Ostick & Williams Belfast